NYPF 2023/2026 Business Plan Update November 2023 Appendix 3
RAG rating:
Green – completed or not yet due
Orange – ongoing, carried forward to 2024/25
Red – outstanding, overdue
Key Activity |
Resource |
|||
Administration |
Head of Pensions Administration |
|||
Action |
Timescale |
Progress Update |
||
McCloud remedy
|
Q3 2023/24 |
In progress – data being checked and updated to records. Missing data being gathered. Project plan created and next steps identified. |
|
|
Data quality improvement |
Q4 2023/24 |
In progress – data cleanse ongoing, records being corrected from issues identified by annual data scoring exercise |
|
|
Backlogs |
Q2 2023/24 |
Completed – backlogs reduced to 4 weeks. Continued review and monitoring is in place to maintain position. |
|
|
Key Activity |
Resource |
|||
Business Improvement |
Head of Pensions Administration |
|||
Action |
Timescale |
Progress Update |
||
Complete roll out of employer portal |
Q4 2023/24 |
In progress – roll out was paused for year-end processing but work has recommenced and additional resource has been added to the project team to increase speed of onboarding. |
|
|
Complete website redevelopment |
Q4 2023/24 |
In progress – user testing completed. Feedback being worked through, on target for go live 1 December 2023. |
|
|
Key Activity |
Resource |
|||
Governance |
Head of Pensions Administration/Head of Investments |
|||
Action |
Timescale |
Progress Update |
||
SAB Good governance project |
Q4 2023/24
|
Unable to progress – still waiting for DLUHC’s response to SAB’s action plan. |
|
|
TPR Single Code of Practice |
Q4 2023/24 |
Unable to progress – still waiting for new code to be issued. |
|
|
Key Activity |
Resource |
|||
Funding |
Pension Fund Committee/ Treasurer/ Head of Investments |
|||
Action |
Timescale |
Progress Update |
||
Income monitoring
|
Q4 2023/24 |
In progress – preliminary discussions held with another Fund using the functionality. Business proposal prepared and submitted to T&C. |
|
|
Key Activity |
Resource |
|||
Investment |
Pension Fund Committee/ Treasurer/ Head of Investments |
|||
Action |
Timescale |
Progress Update |
||
Responsible Investment |
Q4 2023/24
|
TCFD reporting on hold, pending the publication of guidance by the Government. Delay of at least a year expected. In progress – on track to apply for signatory status to new Stewardship Code by the end of the current financial year. |
|
|
Pooling and implementation of investment strategy |
Q4 2023/24 |
In progress – workshops planned Q1 24/25 for UK opportunities, Climate opportunities and UK property as part of due diligence work before recommendations on commitments will be put to the Committee. Review of allocation ongoing. |
|
|